Memorial Field bleacher demolition in Concord, NH nears end of $385,000, five-week job
Crews in Concord, New Hampshire are removing bleachers and foundations at Memorial Field, a $385,000 project begun in mid-July and expected to take about five weeks. The scope includes soil removal, new loam and seed, a reinforced baseball backstop and regrading, following engineering assessments that found the structures code deficient. Temporary bleachers are planned ahead of the September 4 season opener, with electrical work for lights and the PA system remaining a concern.